"The award will be made on either an individual item basis or summary bid basis, whichever results in the lowest cost to the Government. Therefore, to assure proper evaluation of all bids, a bidder quoting a summary bid price must also quote a price on each individual item included in the summary bid price."
A single award will be made on Item No. 1, but in the event the offer exceeds the funds available, a single award will be made on Item No. 2 or Item No. 3, in that order, based on available funding. Offerors should quote a price on each item listed.
Item No. 1-Furnish all labor, material, equipment, etc., to paint Buildings No. 1, 2, and 3: $__.
Alternate items in order of priority:
Item No. 2-Furnish all labor, material, equipment, etc., to paint Building Nos. 1 and 2: $__.
Item No. 3-Furnish all labor, material, equipment, etc., to paint Building No. 1: __.
48 C.F.R. § 814.201