From Casetext: Smarter Legal Research

Zajonc v. Szrzepowski

Supreme Court of Connecticut First Judicial District, Hartford, March Term, 1928
May 4, 1928
141 A. 651 (Conn. 1928)

Opinion

The trial court's finding that the plaintiff had substantially performed his contract to build a house for the defendant at an agreed price of $10,500, which should be a duplicate of one already constructed, was supported by evidence that the items omitted were of minor importance and of a value of only $48. The trial court, having found that certain extras furnished by the plaintiff more than equalled the value of the omitted items and having rendered judgment for the plaintiff to recover the balance due upon the contract price, later corrected the finding by adding that the value of the only extras for which the plaintiff intended to make a charge was $27. Held that while the finding as corrected was not entirely clear, it could be supported upon the ground that the trial court was not bound to accept the valuation placed by the defendants upon the omitted items; and that, in any event, the discrepancy, which could not have exceeded the sum of $21, was too trivial to warrant the granting of a new trial.

Argued March 6th, 1928

Decided May 4th, 1928.

ACTION to recover a balance alleged to be due the plaintiff upon a contract for the construction of a dwelling-house for the defendant, brought to the Superior Court in Middlesex County and tried to the court, Avery, J.; judgment for the plaintiff, and appeal by the defendants. No error.

Leonard O. Ryan, with whom was Alfred LeWitt, for the appellants (defendants).

Thomas C. Flood, for the appellee (plaintiff).


The plaintiff built a house for the defendants for an agreed price of $10,500. There were no plans or specifications, but it was agreed that the house should be built substantially like a certain house in New Britain. The defendants paid $9,500 upon the purchase price, and this action was brought to recover the balance of $1,000 and for extra labor and material claimed to have been furnished at the request of the defendants. The defense was that the plaintiff had failed in certain respects to duplicate the New Britain house. The court found a substantial performance of the plaintiff's contract, that the cost and value of the extra labor and material furnished more than equaled that of the items omitted, and rendered judgment for the plaintiff to recover the balance of the contract price only.

The facts found support the judgment, but defendants seek to have the finding corrected by striking out (1) the finding that the house was constructed substantially like the one in New Britain, and (2) that the cost of the extra work and material more than equaled that of the items omitted. There was evidence in support of both of these findings. The defendants claim that the finding that the house was built substantially the same as the one in New Britain is contradicted by the finding that certain items were omitted. The omitted items are matters of very minor importance, amounting in all, so far as the evidence discloses, to not more than $48. There has clearly been a substantial performance of the plaintiff's contract. Pinches v. Swedish Lutheran Church, 55 Conn. 183, 10 A. 264. The finding lists the items of construction which were in the New Britain house but were not in the house built by the plaintiff for the defendants, but does not place any valuation on them. This paragraph of the finding is not attacked in the motion to correct, but it is necessary to go to the evidence for the value of these items to determine whether there was evidence to support the finding that the value of the extra work and material exceeded that of the omitted items. These omitted items are eight in number; as to only four of them is there evidence in the record of what it would have cost to install them. They are as follows: Connecting rain water leaders with sewer, $40; painting cellar doors, $2; one window cord and weight, $1; matched boards on roof $5; making a total of $48. The other four items are plumbing work. A plumber testified regarding this work and his bill for doing it, but the bill is not in the record nor any evidence as to its amount or as to the reasonable cost of doing the omitted work. As to the omitted items, therefore, the record shows no more than that there was evidence from which the court might have found that their value was not to exceed $48. The court found that the extra labor and material furnished by the plaintiff amounted to $722, but corrected this paragraph of the finding by adding a finding that the plaintiff did not intend to make any extra charge for this beyond the contract price except for some sash amounting to $27. The meaning of this correction when read in connection with the rest of the finding is not entirely clear. It is perhaps susceptible of meaning that, taking the job as it was actually done, with the omissions and the extra work, the plaintiff did not intend to charge anything beyond the contract price except for the item of $27. There was evidence which would support such a construction of the finding and so construed this portion of the finding would not conflict with the finding that the extra work exceeded in value the omitted items. If the finding as corrected means that the only extra work for which any charge was to be made amounted to only $27, this sum is $21 less than the valuation placed by defendants' evidence upon the omitted items. The court was not, however, bound to find the value of these omitted items in exact accord with the defendants' evidence, but upon that evidence might have found that their actual value did not exceed that of the extra sash. Even if the finding were corrected, the correction could extend no further than to find that the omitted items exceeded the extra work in value by the amount of $21, and we would not feel justified in sending the case back for a new trial for so trifling a matter. De minimis non curat lex.

The defendants also asked to have added to the finding a paragraph of their draft-finding to the effect that the plaintiff agreed to enclose the porch with glass without extra charge, but failed to do so. The finding does state that plaintiff did not enclose the porch in glass, but the evidence does not sustain defendants' claim that plaintiff's contract included this work. His contract was to duplicate the New Britain house and one of the defendants testified that the porch on that house was not enclosed. The assignment of error based on the ruling on evidence is without merit.


Summaries of

Zajonc v. Szrzepowski

Supreme Court of Connecticut First Judicial District, Hartford, March Term, 1928
May 4, 1928
141 A. 651 (Conn. 1928)
Case details for

Zajonc v. Szrzepowski

Case Details

Full title:JOSEPH ZAJONC vs. JAN SZRZEPOWSKI ET AL

Court:Supreme Court of Connecticut First Judicial District, Hartford, March Term, 1928

Date published: May 4, 1928

Citations

141 A. 651 (Conn. 1928)
141 A. 651

Citing Cases

Fellows v. Martin

In 1928, considering an appeal on an action to recover the balance due on a $10,500 construction contract, we…