From Casetext: Smarter Legal Research

Tempforce v. Municipal Housing Authority

Appellate Division of the Supreme Court of New York, Third Department
Dec 7, 1995
222 A.D.2d 778 (N.Y. App. Div. 1995)

Summary

holding that “[i]t is well settled that a defendant may not seek contributionfrom other defendants where the alleged ‘tort’ is essentially a breach of contract.”

Summary of this case from BNP Paribas Mortgage Corp. v. Bank of America, N.A.

Opinion

December 7, 1995

Appeal from the Supreme Court, Schenectady County (Lynch, J.).


In 1988 defendant Schenectady Municipal Housing Authority (hereinafter SMHA) decided to replace the roofing system at Yates Village (hereinafter the project), a housing project in the City of Schenectady, Schenectady County. SMHA hired third-party defendant Feibes Schmitt Architects (hereinafter FS) to provide architectural services, defendant McNar Industries, Inc. as general contractor and third-party defendant David Sadowsky, an architect, to oversee the project on its behalf. In 1990 following completion of construction, plaintiff Tempforce, Inc. and plaintiff Bellevue Builders Supply, Inc. commenced an action against SMHA, McNar and others; the cause of action against McNar sounded in breach of contract based upon McNar's alleged failure to pay for labor and materials supplied at the project. In response SMHA asserted a cross claim against McNar seeking delay damages and McNar cross-claimed against SMHA. McNar then commenced a third-party action against FS and Sadowsky seeking damages, contribution and indemnification; in that action McNar asserted that any wrongdoing claimed against it was directly attributed to the negligence, breach of contract and breach of warranty of FS and Sadowsky. FS and Sadowsky each moved for summary judgment seeking dismissal of McNar's third-party complaint and all cross claims against them. Supreme Court, concluding that McNar's third-party action sought damages for breach of contract involving economic loss in the context of a claim for contribution, granted the motions. McNar appeals.

We affirm. McNar contends that its third-party complaint is based upon the "professional performance" of FS and Sadowsky as project architects during the preparations for and completion of the project; McNar claims that FS failed to properly address design defects and unreasonably withheld approval of several necessary material changes and caused delays, and that Sadowsky unreasonably withheld approval of specified products and failed to correct design defects causing McNar to expend substantial time, additional funds and suffer delays. McNar contends that its third-party complaint is based on each architect's "individual, tortious, professional participation on this project and is not a simple contribution/indemnification claim", and that the claimed items of loss are other than pure economic loss in the context of contribution.

It is well settled that a defendant may not seek contribution from other defendants where the alleged "tort" is essentially a breach of contract claim ( see, Sommer v Federal Signal Corp., 79 N.Y.2d 540, 557; Nassau Roofing Sheet Metal Co. v Facilities Dev. Corp., 71 N.Y.2d 599; Board of Educ. v Sargent, Webster, Crenshaw Folley, 71 N.Y.2d 21, 26-29). Because the rules of contribution, as governed by CPLR article 14, are a codification of the Court of Appeals' decision in Dole v Dow Chem. Co. ( 30 N.Y.2d 143), which extended contribution in the context of a tort claim ( see, Sommer v Federal Signal Corp., supra, at 556), the Court of Appeals has stated: "To permit apportionment of liability, pursuant to CPLR 1401, arising solely from breach of contract would not only be at odds with the statute's legislative history, but also do violence to settled principles of contract law which limit a contracting party's liability to those damages that are reasonably foreseeable at the time the contract is formed" ( Board of Educ. v Sargent, Webster, Crenshaw Folley, supra, at 28). Clearly any attempt by McNar to seek contribution from FS and Sadowsky is prohibited.

CPLR 1401 states, in relevant part: "two or more persons who are subject to liability for damages for the same personal injury, injury to property or wrongful death, may claim contribution among them whether or not an action has been brought or a judgment has been rendered against the person from whom contribution is sought."

Further, we conclude that McNar's reliance on Robinson Redevelopment Co. v Anderson ( 155 A.D.2d 755) is misplaced. As observed by Supreme Court, "McNar's artfully drawn pleading can not change the nature of this action from a contract to a tort to enable Third-Party Plaintiff to seek apportionment of liability." In Robinson, the plaintiff, in its primary action, alleged two separate and distinct causes of action, one based upon a breach of contract claim and the other based upon a professional malpractice claim. Under those circumstances we concluded that the cause of action in the third-party complaint seeking contribution could properly be couched upon the malpractice claim in the original complaint, not on the breach of contract claim.

In this case plaintiffs' allegation against McNar and McNar's cross claim against SMHA sound solely in contract. In our view the nature of the primary action is significant. We therefore conclude that Supreme Court properly relied upon the rationale set forth in Board of Educ. v Sargent, Webster, Crenshaw Folley (supra). McNar's third-party complaint, couched upon a pure breach of contract complaint which alleges economic loss only, fundamentally seeks contribution and, therefore, fails to state a cause of action.

Mikoll, J.P., Crew III, Yesawich Jr. and Peters, JJ., concur. Ordered that the order is affirmed, with one bill of costs.


Summaries of

Tempforce v. Municipal Housing Authority

Appellate Division of the Supreme Court of New York, Third Department
Dec 7, 1995
222 A.D.2d 778 (N.Y. App. Div. 1995)

holding that “[i]t is well settled that a defendant may not seek contributionfrom other defendants where the alleged ‘tort’ is essentially a breach of contract.”

Summary of this case from BNP Paribas Mortgage Corp. v. Bank of America, N.A.

finding that while defendant/third-party plaintiff alleged that third-party defendants breached their professional duties, the third-party complaint was dismissed because it was "couched upon a pure breach of contract complaint which alleges economic loss only"

Summary of this case from Highland Capital Management, L.P. v. Schneider
Case details for

Tempforce v. Municipal Housing Authority

Case Details

Full title:TEMPFORCE, INC., Doing Business as TEMPFORCE OF ALBANY, et al.…

Court:Appellate Division of the Supreme Court of New York, Third Department

Date published: Dec 7, 1995

Citations

222 A.D.2d 778 (N.Y. App. Div. 1995)
634 N.Y.S.2d 827

Citing Cases

Metropolitan Steel Indus., Inc. v. Perini Corp.

The Court held that "[t]o permit apportionment of liability, pursuant to CPLR 1401, arising solely from…

Westbank Contracting, Inc. v. Rondout Valley Central School District

Next, we consider Sear-Brown's claims for contribution from third-party defendants. "It is well settled that…