From Casetext: Smarter Legal Research

Prestressed Concrete, Inc. v. Adolfson Peterson

Supreme Court of Minnesota
Mar 26, 1976
308 Minn. 20 (Minn. 1976)

Summary

deciding that two parties in a multiparty suit, who were not agents but separate corporations, could not be compelled to arbitrate their claims

Summary of this case from Onvoy, Inc. v. SHAL, LLC

Opinion

No. 45750.

March 26, 1976.

Actious — multiparty action — claims subject to arbitration — determining severability.

In multiparty actions where some of the parties are contractually bound to arbitrate some of the issues involved, the court will balance the interests of these contractually bound parties against the interests of the other parties and against the policy of the Rules of Civil Procedure to facilitate the joinder of all related parties and issues in determining the severability of the claims subject to arbitration.

Prestressed Concrete, Inc., subcontractor, brought a declaratory judgment action in the Hennepin County District Court against Adolfson Peterson, Inc., general contractor, and the regents of the University of Minnesota, landowner, to determine the rights and obligations of the parties under certain construction contracts. Said regents filed a third-party complaint for indemnity against The Architects Collaborative, Inc., and Carl Walker Associates, Inc. The court, Dana Nicholson, Judge, denied a motion by the first named third-party defendant for dismissal of the third-party complaint and also its motion to compel arbitration. Said third-party defendant appealed from said order. Affirmed.

Cousineau, McGuire, Shaughnessy Anderson, Dean D. Larsen, and Robert McGuire, for appellant.

Briggs Morgan and John L. Devney, for respondent.

Heard before Peterson, Todd, and Scott, JJ., and considered and decided by the court en banc.


The Architects Collaborative, Inc. (TAC) appeals from an order denying its motion for dismissal and for an order compelling arbitration. We affirm.

Prestressed Concrete, Inc. (Prestressed) commenced a declaratory judgment action against Adolfson Peterson, Inc. (AP) and the Regents of the University of Minnesota (University) seeking a determination that it was entitled to damages arising out of its subcontract with AP for the manufacture of precast concrete components for a parking lot being constructed by AP as general contractor for the University. TAC was employed by the University to serve as architects for the project pursuant to a contract which provided for arbitration of any dispute arising out of the agreement. TAC in turn employed Carl Walker Associates, Inc. (Walker) to perform structural engineering services. None of the contracts involved, other than the one between the University and TAC, contained arbitration clauses.

After Prestressed initiated this action, the University commenced third-party proceedings against TAC and Walker seeking indemnity for all damages it sustained in the main action, and further seeking additional consequential damages from TAC and Walker. TAC moved the trial court to compel arbitration of its dispute with the University and to dismiss the third-party complaint. The lower court denied the motion to dismiss the third-party complaint and declined to compel arbitration of the indemnity aspects of that claim, but did stay the determination of the University's claim against TAC and Walker for consequential damages, directing that after the trial of the main action and the indemnity claim, TAC may request reconsideration of its motion to compel arbitration of the damages still in dispute between it and the University.

TAC argues that the trial court erroneously denied its motion to compel arbitration of the entire third-party claim on the grounds that its contract with the University clearly provides for arbitration, that the issues involved are within the intended scope of the arbitration clause, and furthermore, that the determination of what issues fall within the scope of such clause should initially be resolved by arbitration. These arguments would be persuasive if the sole parties to this litigation were TAC and the University. In such a situation, the arbitration clause would be applicable and issues as to its scope could properly be raised.

However, in the context of the present complex multiparty litigation, the precise issue involved is the extent to which an arbitration agreement binding two of the parties should be enforced when their interests and the policies supporting arbitration are balanced against the interests of the other parties and the policies supporting joinder of parties and claims.

TAC relies heavily on the proposition often stated by this court that arbitration is a favored method of dispute resolution. Grover-Dimond Associates, Inc. v. American Arbitration Assn. 297 Minn. 324, 211 N.W.2d 787 (1973), and cases cited therein. However, the fact that arbitration is favored by this court does not mean that it is our favorite remedy in situations where it would jeopardize other favored procedures and policies. Of at least equal stature and importance are our Rules of Civil Procedure, a major purpose of which is to encourage the efficient and expeditious resolution of controversies by facilitating joinder of all related parties and claims. The importance of Rule 14.01, Rules of Civil Procedure, providing for third-party actions, in advancing this favored policy of consolidating related claims and parties into a single lawsuit, is emphasized by the following comments on that rule:

"* * * The purpose for impleading a third-party defendant is to eliminate multiplicity of actions by bringing into the pending litigation all litigants having an interest in the total proceeding and to dispose of the entire matter without the expense and time involved in many separate law suits. Since the purpose is to eliminate multiplicity of claims, courts should be liberal in permitting impleader and should be reluctant to order separate trials of the third-party actions except in the clearest of situations where prejudice will outweigh the desirability of a single trial." 1 Hetland Adamson, Minnesota Practice, Civil Rules Ann., p. 508.

This statement accurately reflects the views of this court in seeking to avoid multiple litigation, and it is this policy which must be balanced against the contractual obligation of TAC and the University to arbitrate disputes arising out of their agreement.

We conclude that paramount policy considerations support the trial court's determination that the litigation should proceed. In arriving at this conclusion, we have considered that of the five parties involved, three cannot be compelled to arbitrate their claims; that the issues involved in the principal action are not subject to arbitration; that TAC can be under no obligation to indemnify the University until there has been a determination that the University is responsible in damages to Prestressed and A P; that Walker's responsibility, if any, is not subject to arbitration; that the arbitration award if filed before the trial could not be binding on the majority of the parties in this action since they are not contractually bound to arbitrate; and that the claim of indemnity did not arise out of the contract between TAC and the University.

In addition, TAC ignores the practicalities of the matter. As we have stated, Prestressed and Walker cannot be bound by any arbitration award. TAC's liability hinges on Walker's performance since Walker is TAC's agent, and any negligence on its part may be imputed to TAC. Consequently, dismissal of the University's action against TAC and Walker from this litigation would only cause delay and confusion. The basis for the favored status which arbitration usually enjoys in this court — that it generally expedites the settlement of disputes simply, clearly, and inexpensively — just is not present in this case. Where arbitration would increase rather than decrease delay, complexity, and costs, it should not receive favored treatment. See, Niazi v. St. Paul Mercury Ins. Co. 265 Minn. 222, 231, 121 N.W.2d 349, 355 (1963).

Therefore, we conclude that under the facts of this case policy considerations support the lower court's refusal to compel arbitration of the entire third-party claim or to dismiss that claim. We further note that the lower court's stay of proceedings as to the University's claim against TAC for consequential damages was proper, since it appears that this matter is probably required to be arbitrated under the contract between the University and TAC.

Affirmed.


Summaries of

Prestressed Concrete, Inc. v. Adolfson Peterson

Supreme Court of Minnesota
Mar 26, 1976
308 Minn. 20 (Minn. 1976)

deciding that two parties in a multiparty suit, who were not agents but separate corporations, could not be compelled to arbitrate their claims

Summary of this case from Onvoy, Inc. v. SHAL, LLC

In Prestressed Concrete, Inc. v. Adolfson Peterson, Inc., 308 Minn. 20, 240 N.W.2d 551 (1976), the Minnesota Supreme Court, noting the majority rule that arbitration is generally encouraged as an alternative to a judicial tribunal, Ford Motor Co. v. M/S Maria Gorthon, 397 F. Supp. 1332 (D.Md. 1975); Leeward Bus Co. v. City and County of Honolulu, 58 Haw. 64, 564 P.2d 445 (1977), further recognized that this dictate must frequently be considered in light of the equally favored position of promoting "the efficient and expeditious resolution of controversies by facilitating joinder of all related parties and claims."

Summary of this case from Loomis, Inc. v. Cudahy

In Prestressed Concrete, Inc. v. Adolfson Peterson, Inc., 308 Minn. 20, 22-23, 240 N.W.2d 551, 553 (1976), the supreme court held that in complex multi-party actions in which some of the parties are contractually bound to arbitrate, the policies supporting arbitration will be balanced against the interests of parties not subject to the arbitration agreement and against the policy behind the Rules of Civil Procedure which encourage the efficient resolution of controversies by facilitating joinder of all related parties and claims.

Summary of this case from Personalized Marketing v. Stotler Co.

In Prestressed Concrete, Inc. v. Adolfson Peterson, Inc. (1976), 308 Minn. 20, 240 N.W.2d 551, the Minnesota Supreme Court considered the extent to which an arbitration agreement binding two of the parties should be enforced when their interests and the policies supporting arbitration are balanced against the interests of the other parties and the policies supporting joinder of parties and claims.

Summary of this case from J.F. Inc. v. Vicik

In Prestressed Concrete, Inc. a subcontractor brought an action for damages against the owner and the general contractor, and the owner, in turn, counterclaimed against its architect and engineer for indemnity and damages.

Summary of this case from Iser Electric Co. v. Fossier Builders, Ltd.
Case details for

Prestressed Concrete, Inc. v. Adolfson Peterson

Case Details

Full title:PRESTRESSED CONCRETE, INC. v. ADOLFSON PETERSON, INC., AND ANOTHER. THE…

Court:Supreme Court of Minnesota

Date published: Mar 26, 1976

Citations

308 Minn. 20 (Minn. 1976)
240 N.W.2d 551

Citing Cases

Loomis, Inc. v. Cudahy

Several courts have had the opportunity to examine the issues presented by an arbitration agreement in the…

Stillwater, Etc. v. Kraus-Anderson Const

On February 12, 1981, Stillwater, in response to Kraus-Anderson's arbitration demand, brought a motion in…