From Casetext: Smarter Legal Research

Montgomery v. Kimbrough Homes

Supreme Court of Mississippi
Jun 9, 1952
59 So. 2d 273 (Miss. 1952)

Opinion

No. 38460.

June 9, 1952.

1. Appeal — peremptory instruction — effect of.

Where a peremptory instruction has been granted to the defendant, the evidence on appeal will be considered in the light favorable to the plaintiff.

2. Contracts — builder's contract — breach.

When there has been a breach of a builder's contract, as the jury was authorized to find under the evidence, an obligation arose by virtue of such breach, which as such needed neither ratification nor supplemental agreement.

3. Contracts — builder's contract — practice of ignoring floor plans.

Where the plans for a building consisted of two sheets of blue print drawings, the first sheet for the foundation, and the second for the dimensions and location of the rooms, and the latter called for floor plans approximately two feet larger than those shown on the foundation plans and the contractor examined only the foundation plan and thereupon made his bid for the building which was accepted, the practice to ignore the floor plans until that state of construction had been reached did not acquit the contractor of negligence or responsibility in this respect.

4. Contracts — building contracts — increased costs.

When the building contractor had begun the work on the foundation without examination of the inconsistent floor plans, as mentioned in the foregoing headnote, and thereupon utilized the expense and delay of enlarging or taking out the foundation as a pressure upon the owner to allow the work to proceed thus practically nullifying the interior floor plans, the increased cost of taking out and enlarging the foundation was not available to the contractor as a defense.

5 Damages — builder's contract — error in failure to comply with specification.

In the case outlined in the foregoing headnote and in an action for the breach of the builder's contract the proper test is not the cost to the contractor of rectifying the error but the damage to the owner by the failure to do so.

6. Contracts — builder's contract — waiver.

Where the owner had protested against the work being done to fit the foundation plan instead of the floor plan, and consented only after the pressure exerted on him heretofore mentioned and on assurance of later adjustment, his consent constituted no waiver of his right of action for damages.

7. Contracts — building contracts — contractor's duty to verify all dimensions.

Where building plans submitted to the building contractor contained the provision that the "contractor shall check and verify all dimensions", it was the duty and responsibility of the contractor to comply with that provision before bidding on the building or beginning on the construction of it, and this although the owner had had the plans prepared.

8. Contracts — building contracts — owner's affidavit to title company.

Although in order to procure a loan to pay the contractor the amount of his bid, the owner made an affidavit for a title company that the house had been constructed according to contract and was "in all things satisfactory", this did not bar the owner's action for damages, but was available to the contractor only as circumstantial evidence to support a contention of compliance or waiver.

9. Contracts — building contracts — approval by Federal Housing Administration.

A building contract provided that "the said dwelling house shall be constructed to the satisfaction of Federal Housing Administration minimum standards and said institution shall be the final judge of any and all construction requirements": Held, that inasmuch as the Administration could be satisfied by a compliance with the requirements which fall short of the legal duty of the contractor under the builder's contract, such approval would in no sense absolve the contractor of any legal duty to the owner under such contract.

Headnotes as approved by Alexander, J.

APPEAL from the circuit court of Hinds County; M.M. McGOWAN, Judge.

Dan E. Breland, for appellants.

I. The judgment of the circuit court is contrary to the law applicable to this case.

(A) The appellants have a good cause of action. Lowe v. Mobile O.R. Co., 149 Miss. 889, 116 So. 601.

(B) The fact that Federal Housing Administration issued mortgage insurance on the house does not bar appellants from recovering damages suffered by them where the size of the house was reduced by appellee. Standard Mill Work Supply Co. v. Mississippi Steel Iron Co., 205 Miss. 96, 38 So.2d 448; Helm, et al. v. Speith, et al., (Ky.), 182 S.W.2d 635; Speith, et al. v. Helm, et al., 301 Ky. 451, 192 S.W.2d 376; Zimmerman v. Marymor, 290 Pa. 299, 138 A. 824; Small v. D.J. Lee Bros., 4 Ga. App. 395, 61 S.E. 831.

(C) Assuming, but not conceding, that Federal Housing Administration did have the capacity and did act as arbiter, appellants would not be bound thereby because the evidence is undisputed that the size of two of the rooms in the house are smaller than required by and under the plans. 9 Am. Jur., Building and Construction Contracts. par. 36, Conclusiveness of Decision or Certificate, par. 38, Impeachment of Decision or Certificate; Ilse v. Aetna Indemnity Co., 55 Wn. 487, 104 P. 787; Guarantee Title T. Co. v. Willis, 38 Ariz. 33, 297 P. 445, 110 A.L.R. 142; 137 A.L.R. 531 under the annotation, "Right of Architect or Engineer to Construe Building or Construction Contract".

(D) Appellants safely preserved their rights in order to enforce their claims against appellee. Kendrick v. White, (Ga.), 43 S.E.2d 285; 56 Am. Jur., Waiver, pars. 2, 15, and 21.

II. The judgment of the circuit court is against the overwhelming weight of the evidence and is manifestly wrong. 3 Am. Jur., Appeal and Error, pars. 886, 888; St. Louis S.F.R. Co. v. Moore, 101 Miss. 768, 58 So. 471; Stovall v. Farmers' M. Bank, 8 S. M. 305; Hardin, et ux. v. Beaman, 49 So.2d 732; Burrowes Co. v. Crittenden, 37 So. 504.

Crisler Crisler, for appellee.

I. The circuit court did not err in ruling that the county court was in error in failing to grant a peremptory instruction to the jury to find for the defendant.

(A) The undisputed evidence in the record discloses without question that the practical construction placed by the parties by their actions on the ambiguity contained in the written building agreement as to the size of the house to be built thereunder established without question that appellee built for the house which was in fact contracted for. Adalex Construction Co. v. Adkins, et al., 214 Ala. 53, 106 So. 338; A. S. Spengler v. Stiles-Tull Lbr. Co., 94 Miss. 780, 48 So. 966; Bracey v. Crisler, 151 Miss. 655, 118 So. 138; Candler v. Cromwell, 101 Miss. 161, 57 So. 554; Darden v. American Bank Trust Co., 158 Miss. 742, 130 So. 507; Granberry v. Mortgage Bond Trust Co., 159 Miss. 460, 132 So. 334; Moselage v. Benevolent Protective Order of Elks, 118 Miss. 5, 78 So. 947; Newman v. Supreme Lodge, Knights of Pythias, 110 Miss. 371, 72 So. 241; Pratt v. Canton Cotton Co., 51 Miss. 470; R.B. Tyler Co. v. Laurel Equipment Co., 187 Miss. 590, 192 So. 573; Sumter Lbr. Co. v. Skipper, 183 Miss. 595, 184 So. 296; 17 C.J.S., Sec. 325. p. 755.

(B) Certification by the Federal Housing Authority that the dwelling in controversy was acceptably completed in accordance with its minimum standards was binding on the parties to the contract in the absence of fraud or mistake and no fraud or mistake was alleged in the pleadings and none appears from the record. Carlson, et ux. v. Len Home Builders, Inc., 132 N.J. eq. 38, 26 A.2d 576; Helm, et al. v. Speith, et al., 301 Ky. 451, 182 S.W.2d 635, 192 S.W.2d 376; Farrell v. Levy, 139 App. Div. 790, 124 N.Y. Supp. 439, 54 A.L.R. 1268; Mercer v. Harris, 4 Neb. 77, 54 A.L.R. 1268; Smith v. Copiah County, 239 Fed. 425; Standard Construction Co. v. Brantley Granite Co., 90 Miss. 16, 43 So. 300; Standard Millwork Supply Co. v. Mississippi Steel Iron Co., 205 Miss. 96, 38 So.2d 448; 9 Am. Jur., Sec. 36, p. 26; 54 A.L.R. 1260.

(C) The trial court erred in permitting the appellants to file a denial as to the special matter set forth in the answer of appellee, after the jury had been selected, the trial of the cause commenced and considerable testimony adduced from the appellant Montgomery — therefore, the allegation of the appellee that the appellants agreed as to the size of the dwelling to be constructed is confessed, and no issue was made up to be submitted to the jury. Sec. 1475.5 Code 1942.

(D) The law of waiver is not properly applicable to this case, but even under that principle, appellee was entitled to a peremptory instruction in its favor. 56 Am. Jur., Sec. 13, p. 113; Moselage v. Benevolent Protective Order of Elks, supra.

II The trial court erred in granting instruction No. One for appellants and refusing instruction No. Three for appellee. Harris v. Williams, (Miss.), 43 So.2d 365; Baldwin v. McKay, 41 Miss. 358; Young v. Power, 41 Miss. 197.


Appellants brought an action for damages asserted as having arisen from a breach of a building contract by appellee. From a verdict and judgment in the County Court for the plaintiff an appeal was taken to the Circuit Court where the judgment was set aside on the ground that, under the record, the defendant's request for a directed verdict had been erroneously refused.

The contract as shown by plaintiffs consists of two sheets of blueprint drawings which were furnished to the defendant as the basis for his construction bid thereon which was accepted.

There is no question but that the specifications laid out on the first sheet which covered the foundation plan, and those upon the second sheet laying out the dimensions and locations of the rooms, are irreconcilable. The latter calls for a floor plan approximately two feet larger than those shown on the foundation plan. This discrepancy was called by the plaintiffs to the attention of a representative and general agent of the defendant who was supervising the construction. He was instructed by the defendant to disregard this inconsistency. There were assurances given by such representative that some adjustment would be made but that the cost of razing the foundation so as to enlarge it would be prohibitive in cost. The complaints persisted and plaintiffs were told by Mr. Kimbrough that he would brook no delay in completing the financial arrangements. Such details involved a certificate of acceptance of a loan to be guaranteed by the Federal Housing Administration, and a certificate by plaintiffs for the information of a title company, in which they certified by affidavit that the house had been completed according to plans and specifications. The defendant exerted considerable pressure upon the plaintiffs to consummate the loan from whose proceeds it was to receive payment under the contract. Such insistence was backed by a threat of eviction, which in turn employed the leverage of plaintiffs' need for immediate housing.

(Hn 1) The foregoing recitals, while contradicted, are drawn up in the plaintiffs' favor since the alleged error is based upon the giving of a peremptory instruction for the defendant. There were many details, some of which are vague, but which add up to the fact of a two foot disparity between the two sheets of blueprints. Testimony as to the extent of damage to plaintiffs included estimates of the added cost to build the house two feet wider, and of the comparative values of the house as planned and as constructed. The inconveniences caused to plaintiffs and the financial disadvantages incident to the asserted impossibility of renting one of the rooms in its existing dimensions were also included in the demand.

The arguments by the defendant, appellee here, revolve about the fact that the plans were prepared at the instance of the plaintiffs and the errors are solely their own; that there was no definite or enforceable agreement to adjust the damages at defendant's expense; that plaintiffs accepted the house as completed and certified that it conformed to the specifications.

On the other hand, the plaintiffs contend that the Federal Housing Administration was not a final arbiter as to the compliance with the plans; that the certificate and affidavit were addressed not to the defendant but to a title guaranty company; and that the work was allowed to continue under protest and with an assurance of an adjustment in the final cost.

(Hn 2) The circuit court rendered an opinion in support of his action in dismissing the case in which it was held that the assurances of a reasonable adjustment or allowance in cost by Kimbrough and his representative, if such be a fact, would not create an obligation upon the defendant because of a lack of authority in the agent, a lack of consideration, and the uncertainty of the terms of the so-called new agreement. We are unable to go along with this conclusion. The jury was authorized to find whether there had been a breach of the original contract, and if so, an obligation arose by virtue of such breach and needed neither ratification nor supplemental agreement. (Hn 3) It was further held that Kimbrough examined only the first sheet of the plans, made his bid thereon, and began construction without reference to the second sheet. Such procedure was sought to be justified by a practice to ignore the floor plans until that stage of construction had been reached. The jury was not bound to acquit the defendant of negligence or responsibility in this respect. (Hn 4) For this reason, the increased cost of taking out and enlarging the foundations is not available to the defendant who utilized the fact of delay and expense incident thereto as pressure upon the plaintiffs to allow the work to proceed, thus practically nullifying the interior floor plans. (Hn 5) The proper test is not the cost to the defendant of rectifying the error, but the damage to the plaintiffs by the failure to do so. (Hn 6) As stated above, the consent by the plaintiffs that the work be not thus delayed is not, in view of their protest and the assurances of later adjustment, of itself a waiver. If the matter of a new consideration is relevant at all it could as plausibly find place in denying to the defendant the right so to alter the contract to its advantage without consideration.

(Hn 7) The circuit judge further found immaterial the following language upon the second page of the plans: "Contractor shall check and verify all dimensions". We think it is probably the most pertinent part of the contract. It was the breach of such undertaking which caused the entire damage. We agree with the court's finding on this point that "If the discrepancy had been discovered, it is safe to assume that there would have been a renegotiation (of the contract)." Such evident fact, however, was charged not against the contractor but against the Montgomerys. Plaintiffs were under no legal duty to check the plans. The defendant came under this duty when he accepted the contract. It is true that the owners had the plans prepared but this is immaterial. The responsibility for checking and verifying all dimensions was assumed by the defendant who accepted the plans and contracted to build the house in conformity therewith. The owner was not bound by the defect in the plans as a legal consequence of submitting them for construction bids thereon. If it was the duty of the plaintiffs to check the dimensions before submission it was all the more the duty of the contractor to do so before bidding and construction. His duty is enhanced by his greater responsibility and ability to do so, and further heightened by the language of the contract. Compare Lonergan v. San Antonio Loan Trust Co., 101 Tex. 63, 104 S.W. 1061, 106 S.W. 876, 22 L.R.A., N.S., 364. Moreover, since the inconsistency was readily found early in the construction it could, and therefore should, have been discovered at the outset.

While the quoted undertaking is brushed aside, (Hn 8) emphasis is placed upon the affidavit executed by the plaintiffs for the purpose of procuring a loan from an insurance company This affidavit certified that the house had been constructed according to the contract and specifications and was "in all things satisfactory". Such affidavit was not a part of the contract. Its purpose was to aid defendant in getting prompt payment of the amount of his bid from the proceeds of the loan. It was not made to defendant but, as above stated, for a title company. Regardless of its pertinency as circumstantial testimony to support a contention of compliance or waiver, it was not ex proprio vigore a bar to plaintiffs' claim. Kendrick v. White, 75 Ga. App. 307, 43 S.E.2d 285; Small v. D.J. Lee Bros., 4 Ga. App. 395, 61 S.E. 831; Zimmerman v. Marymor, 290 Pa. 299, 138 A. 824, 54 A.L.R. 1252. Certainly the execution, for such purpose on the same document, of a similar sworn statment by the defendant could not aid its cause, especially since Kimbrough testified that the two sheets of plans were later found by him to be incongruous. The facts in this case do not fall into a design exactly duplicated elsewhere although there are numerous cases involving the mere incident of ambiguity.

Although the suit is upon a contract, none was exhibited with the declaration. It rests solely upon the undertaking by the defendant to build the house at a fixed bid in accordance with the terms of the blueprints. It is true that in its answer the defendant pleaded and exhibited a written contract which provided in Article 4: (Hn 9) "The said dwelling house shall be constructed to the satisfaction of Federal Housing Administration minimum standards and said institution shall be the final judge of any and all construction requirements."

Such provision did not constitute the Federal Housing Administration as a final arbiter with respect to differences or legal rights of the parties inter sese, especially as to the size and arrangement of rooms. So long as the house was built in conformity with minimum standards of construction its approval would be forthcoming. Such approval in no sense absolved defendant of any legal duty owed to plaintiffs. The Administration could be satisfied by a compliance with requirements which fall short of the satisfaction of the plaintiffs or of the legal duty of the defendant. Helm v. Speith, 298 Ky. 225, 182 S.W.2d 635; Speith v. Helm, 301 Ky. 451, 192 S.W.2d 376.

The verdict of the jury in the county court was rendered under instructions which authorized them to find whether there had been a breach of the contract by the defendant, which in turn involved any duty of the latter to follow the directions therein, and whether the shortage in dimensions resulted from a breach of the contract. The record contains no assignment of error to the circuit court, a procedure which that court would better have required in the interest of an orderly procedure. However, there is no cross-appeal here attacking the instructions given to plaintiffs. The defendant procured an instruction submitting the issue whether the contract was breached, and also authorizing the jury to find for it if the jury believed "that the error in the size of the subject dwelling house resulted because of the defective plans furnished the defendant by the plaintiff." Our discussion of the effect of such circumstance indicates what may be understated as quite a liberal instruction.

The plaintiffs sued for damages in the sum of one thousand dollars which allegedly included the depreciated value of the house and its nonadaptability to the comfort of and use by the plaintiffs. The verdict for four hundred and fifty dollars could be supported alone by the diminished cost of construction at the smaller dimension computed on a square foot basis under the testimony. Plaintiffs contend, however, not only that they paid too much but also that they got too little.

The peremptory charge should not have been granted but the judgment of the county court ought to have been affirmed. Such order will therefore be entered here.

Reversed and judgment here for appellants.

McGehee, C.J., and Hall, Holmes and Ethridge, JJ., concur.


Summaries of

Montgomery v. Kimbrough Homes

Supreme Court of Mississippi
Jun 9, 1952
59 So. 2d 273 (Miss. 1952)
Case details for

Montgomery v. Kimbrough Homes

Case Details

Full title:MONTGOMERY, et ux. v. KIMBROUGH HOMES, Inc

Court:Supreme Court of Mississippi

Date published: Jun 9, 1952

Citations

59 So. 2d 273 (Miss. 1952)
59 So. 2d 273

Citing Cases

Fox v. Webb

Electric Light Co. v. Elder, supra; Northen v. Tatum, 164 Ala. 368, 51 So. 17. Provision in contract that…

Mullins v. Wroten

II. Where the Trial Court directed a verdict for the defendant and the plaintiff appealed, for the purposes…