From Casetext: Smarter Legal Research

Freel v. County of Queens

Appellate Division of the Supreme Court of New York, Second Department
Oct 1, 1896
9 App. Div. 186 (N.Y. App. Div. 1896)

Summary

In Freel v. County of Queens (9 App. Div. 186; S.C., 154 N.Y. 661) the commissioners were subject to the board of supervisors, who, in fact, made the contract; being so subject, it was held that they had no power to modify the contract.

Summary of this case from In re Lent

Opinion

October Term, 1896.

D.E. Delavan, for the appellant.

William C. De Witt, for the respondent.


In the year 1892 the board of supervisors of the county of Queens, by two resolutions, directed the improvement of certain highways in the town of Jamaica, in that county. By these resolutions certain named persons were appointed commissioners to take charge of and superintend such improvements, and the commissioners were authorized to make all necessary contracts for doing the work. The commissioners were directed to prepare plans and specifications and all other instruments in writing, necessary in the course of the work; "provided, however, that all such plans, specifications, contracts and other instruments in writing shall be submitted to this board for its approval as to form and sufficiency before being signed by said commissioners, and provided further that proposals for the doing of such work shall first be publicly advertised for, as directed by section 4 hereof." In pursuance of this authority the commissioners entered into written contracts with the plaintiff for improving certain highways. The contracts for the several highways were all of the same general form and were entered into in pursuance of advertisements for proposals made by the commissioners and of bids made by the contractor in answer thereto. The advertisement for proposals gave the engineer's estimate of the quantities and qualities of the work, but expressly stated that the quantities were approximate only and required any bidder to satisfy himself as to the accuracy of the estimate.

It was further expressly provided that: "No extra compensation beyond the amount payable for the several classes of work before enumerated, which shall be actually performed, at the prices therefor to be specified by the lowest bidder, shall be due or payable for the entire work."

It was further specified that no deviation from the specifications would be allowed unless written permission should have been previously obtained from the commissioners and that "work or material not specified and for which a price is not named in the contract will not be allowed for." The bidders were required to state a price per running foot for completed pavement. The bid of the plaintiff stated that he had examined this request for proposals and the proposed contract, and offered to contract for all the work for a specified price per running foot of completed pavement. By the contract subsequently executed by the parties the plaintiff "admits and agrees that the amounts and quantities of materials to be furnished and work to be done, as stated in the proposals for estimates for the said work, are approximate only, * * * and that he covenants and agrees that he will do the entire work to the satisfaction of the said commissioners, and in substantial accordance with said specifications, and that he will not ask, demand, sue for or recover for the entire work an extra compensation beyond the amount payable for the several classes of work in this contract enumerated, which shall be actually performed at the prices therefor herein agreed upon and fixed." The claim in this action is for an unpaid balance of the contract price for the improvement of the Merrick road and for extra work done in the pavement of Van Wyck avenue and Broadway. The items of extra work claimed by the plaintiff and allowed by the referee were for loam spread on Broadway and Van Wyck avenue; for labor in surfacing Van Wyck avenue, and for screenings thereon; for Roa Hook gravel furnished for Broadway, and for excavations and hauling on that street, amounting in all to $11,130.

We are inclined to the opinion that, assuming it was within the power of the commissioners to modify the contract and order extra work, the plaintiff has not shown himself entitled to recover for the work in suit, except for the unpaid balance of the contract price for the Merrick road. The contract was drawn to preclude claims for extra work of the character of that here presented. The plaintiff expressly admitted that the amounts and quantities of materials stated in the advertisement for estimates were approximate only, and stipulated that he would not ask, demand or sue for extra compensation for the several classes of work enumerated in the contract, and as to the work of a class not enumerated in the contract, and for which no price was named, should not be allowed anything therefor.

It is apparent from the testimony that the commissioners did not assume to modify the contract. The plaintiff was referred by them to the engineer and directed to comply with his instructions in the performance of the work. In the main the work done by the plaintiff was not directed to be performed as additional to or outside of the contract, but as in the proper performance thereof. The plaintiff's foreman testifies that such work "didn't help the road a bit, but we had to do it or stop the work. * * * I declined to do it. The result was we had to do it or stop; it was necessary, because the commissioners told us that we must do as the engineer says." Therefore, when the plaintiff yielded to the demand of the engineer or commissioners to perform such work, he acceded to their contention that the work was necessary to the proper performance of the contract.

As to the item of the Roa Hook gravel, the evidence seems to support the plaintiff's claim that this was in excess of the contract material. It was testified that the foreman, having suggested to the engineer that this gravel was the best covering, the engineer agreed to order it if the commissioners would authorize it. For 500 yards actually used the plaintiff received additional pay. The claim in suit is for the value of 300 yards delivered at the work but not used. This quantity the plaintiff claims was rendered worthless, because the engineer stopped him from further using that material. As to this item the claim is not, in truth, for extra work, but for a breach of the contract to take the material. Such a claim was not alleged in the complaint, nor do we find the evidence sufficient to show that there was an agreement to receive any definite amount. The plaintiff would, therefore, not be entitled to recover the value of this material.

But however this may be, we are clear that the commissioners had no power to impose on the county any liability for work outside of and beyond the provisions of the contract. The commissioners were public officers. Their sole authority to bind the county proceeded from the resolutions enacted by the board of supervisors. All persons dealing with them were bound to ascertain the limits of their powers and authority, and are chargeable with knowledge of such limits. ( Lyddy v. Long Island City, 104 N.Y. 218; Donovan v. The Mayor, 33 id. 291.)

The resolutions did not constitute the commissioners sole judges of the improvements to be prosecuted, or authorize them to make such contracts for the improvements as they deemed proper. The grant of authority to the commissioners was expressly subject to the provision that not only the plans and specifications of the improvements, but also the contracts for its performance, should be submitted to the board of supervisors for approval. If the work done by the plaintiff is not within the terms of the specifications, then the commissioners were not authorized to contract for its performance, for it is only work required by the specifications approved by the board of supervisors that the commissioners were authorized to contract for or prosecute. If within the requirements of the specifications, then, by the express terms of the contract, the plaintiff is not entitled to recover for such work. The only power given the commissioners was to execute a contract previously approved by the board of supervisors. A modification of an existing contract without such approval would be as invalid as the execution of an original contract without complying with this provision of the resolutions. While it was intended that the commissioners should not only have charge and superintendence of the physical prosecution of the work, but should also, in the first instance, determine what the work should be and what character of contract should be made therefor, still it was also intended that the action of the commissioners, in the latter respects, should not become final or operative, except with the assent and approval of the board of supervisors; and it was further intended that no liability should be imposed on the county, except in pursuance of a contract approved by that board and awarded after advertisement. Therefore, no action of the commissioners, except when had in strict compliance with the authority vested in them by the board of supervisors, could in any wise bind the county.

As to the first item of the plaintiff's claim, the unpaid balance of the contract price, we think this was properly allowed to plaintiff. There is no evidence in the case sufficient to show that he forfeited this amount by his failure to perform the work in time. On this question the burden of proof was upon the defendant, and it was bound to establish affirmatively that it was entitled to retain the money.

The judgment appealed from should be reversed and a new trial granted before a new referee, costs to abide the event, unless the plaintiff stipulates to reduce the amount found due to him to the sum of $1,730, with interest from January 1, 1894, in which case the judgment, as reduced, should be affirmed, without costs to either party.

All concurred.

Judgment reversed and new trial granted before a new referee, costs to abide the event, unless plaintiff stipulates within twenty days to reduce the amount found due to him to the sum of $1,730, with interest from January 1, 1894, in which case the judgment so reduced is affirmed, without costs of appeal.


Summaries of

Freel v. County of Queens

Appellate Division of the Supreme Court of New York, Second Department
Oct 1, 1896
9 App. Div. 186 (N.Y. App. Div. 1896)

In Freel v. County of Queens (9 App. Div. 186; S.C., 154 N.Y. 661) the commissioners were subject to the board of supervisors, who, in fact, made the contract; being so subject, it was held that they had no power to modify the contract.

Summary of this case from In re Lent
Case details for

Freel v. County of Queens

Case Details

Full title:EDWARD FREEL, Respondent, v . THE COUNTY OF QUEENS, Appellant

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Oct 1, 1896

Citations

9 App. Div. 186 (N.Y. App. Div. 1896)
41 N.Y.S. 68

Citing Cases

In re Lent

( Matter of Underhill, supra.) In Freel v. County of Queens ( 9 App. Div. 186; S.C., 154 N.Y. 661) the…

Lindlots Realty Corp. v. County of Suffolk

The resolution constituted the only authority to bind the county. Any one accepting a deed from the county…