From Casetext: Smarter Legal Research

Ebasco Constructors, Inc. v. A.M.S. Constr

Appellate Division of the Supreme Court of New York, Second Department
Jul 6, 1993
195 A.D.2d 439 (N.Y. App. Div. 1993)

Summary

In Ebasco, settlements clause, like the clause here, provided that the surety had the right to settle any claim upon the bonds, unless the contractor requested that the surety litigate gate such a claim and deposited with the surety collateral to be used in paying any judgment and costs.

Summary of this case from General Accident Insurance Co. of America v. Merritt-Meridian Construction Corp.

Opinion

July 6, 1993

Appeal from the Supreme Court, Westchester County (Delaney, J.).


Ordered that the order is modified, on the law, by deleting the provisions thereof which vacated the prior order dated September 28, 1990, and denied the motion for summary judgment, and substituting therefor provisions (1) adhering to the original determination granting summary judgment, and (2) amending the prior order to grant the appellant prejudgment interest; as so modified, the order is affirmed, without costs or disbursements, and the matter is remitted to the Supreme Court, Westchester County, for further proceedings in accordance herewith.

It cannot be said that the Supreme Court erred in granting reargument. A motion for reargument is addressed to the sound discretion of the court which decided the prior motion and reargument may be granted upon a showing that the court "overlooked or misapprehended the facts or law or for some reason mistakenly arrived at its earlier decision" (Rodney v. New York Pyrotechnic Prods. Co., 112 A.D.2d 410, 411 [emphasis supplied]). An allegation of new material facts is necessary for renewal, but not reargument (see, Delcrete Corp. v. King, 67 A.D.2d 1099).

However, while reargument was properly granted here, the court should have adhered to the original determination granting the appellant summary judgment. The defendant A.M.S. Construction Co., Inc. (hereinafter A.M.S.) and the third-party defendants issued to the surety International Fidelity Insurance Company general indemnity agreements to induce the surety to issue a performance bond required under A.M.S.'s contract with Ebasco Constructors, Inc. (hereinafter Ebasco). The indemnity agreements provided the surety with the right to settle any claim, unless the indemnitors requested the surety to defend the claim and simultaneously deposited with the surety collateral sufficient to pay any judgment. The indemnitors also agreed to pay the surety for any disbursements made in good faith in connection with the bond. Thereafter, the surety settled a claim against A.M.S. by Ebasco.

In light of the indemnitor's failure to deposit collateral with the surety upon demand, the surety had a right under the indemnification agreements to settle the claim. Moreover, notwithstanding any possible defenses, we cannot find an absence of good faith on the part of the surety. Therefore, the surety was entitled to summary judgment against the indemnitors (see, Maryland Cas. Co. v. Grace, 292 N.Y. 194; Home Indem. Co. v Wachter, 115 A.D.2d 590). In light of the foregoing, the matter must be remitted to the Supreme Court, Westchester County, for an award of interest. Under the circumstances of this case the surety is entitled to prejudgment interest pursuant to CPLR 5001. Rosenblatt, J.P., Copertino, Pizzuto and Joy, JJ., concur.


Summaries of

Ebasco Constructors, Inc. v. A.M.S. Constr

Appellate Division of the Supreme Court of New York, Second Department
Jul 6, 1993
195 A.D.2d 439 (N.Y. App. Div. 1993)

In Ebasco, settlements clause, like the clause here, provided that the surety had the right to settle any claim upon the bonds, unless the contractor requested that the surety litigate gate such a claim and deposited with the surety collateral to be used in paying any judgment and costs.

Summary of this case from General Accident Insurance Co. of America v. Merritt-Meridian Construction Corp.

In Ebasco Constructors v. A.M.S. Const. Co., 195 A.D.2d 439 (2d Dept 1993), the Second Department held, "[i]n light of the indemnitor's failure to deposit collateral with the surety upon demand, the surety had a right under the indemnification agreements to settle the claim."

Summary of this case from Cava Constr. & Dev. Inc. v. Tower Ins. Co. of N.Y.
Case details for

Ebasco Constructors, Inc. v. A.M.S. Constr

Case Details

Full title:EBASCO CONSTRUCTORS, INC., Plaintiff, v. A.M.S. CONSTRUCTION Co., INC.…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Jul 6, 1993

Citations

195 A.D.2d 439 (N.Y. App. Div. 1993)
599 N.Y.S.2d 866

Citing Cases

Cava Constr. & Dev. Inc. v. Tower Ins. Co. of N.Y.

The burden now shifts to the Indemnitors to prove that there is a triable issue of fact regarding the…

W. Sur. Co. v. Steuerwald

Some New York cases suggest that that Mr. Steuerwald's failure to post collateral, as required by the terms…