Assurance Co. of America v. Premium Constr. Grp., Inc.

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE
May 21, 2012
CASE NO. C11-1662 MJP (W.D. Wash. May. 21, 2012)

Opinion

CASE NO. C11-1662 MJP

05-21-2012

ASSURANCE COMPANY OF AMERICA, Plaintiff, v. PREMIUM CONSTRUCTION GROUP, INC., and SEAVESTCO, INC., Defendants.


ORDER DENYING DEFENDANT SEAVESTCO INC.'S MOTION FOR SUMMARY JUDGMENT

This matter comes before the Court on Defendant Seavestco Inc.'s motion for summary judgment. (Dkt. No. 31.) Having reviewed the motion, Plaintiff Assurance Company of America's response (Dkt. No. 39), Defendant Premium Construction Group's response (Dkt. No. 37), the reply (Dkt. No. 44), and all related papers, the Court DENIES the motion.

Background

This is a negligence and breach of contract case brought by an insurance company as subrogee to a developer who incurred substantial expenses repairing damage to a commercial structure it created in Woodinville. Plaintiff Assurance is the insurer of Wellington Hills Park, LLC ("Wellington"), the developer of the Wellington Business Park ("Project"). Assurance alleges that during Seavestco's work on the project it allegedly blocked drain pipes leading from retaining walls causing water to accumulate and displace the walls (Compl. at ¶¶ 10-12.) Following the discovery of the retaining wall failure in December 2008, Wellington submitted a claim to Assurance for property damage relating to the failure of the retaining wall. (Dkt. No. 25 at 1.) Assurance paid $2,878,440.47 to indemnify Wellington for amounts Wellington paid to repair the property damage. (Id. at 1-2.)

Assurance insured Wellington throughout the construction of the Project under a commercial inland marine insurance policy, number EC 4366203 ("Policy"). (Dkt. No. 42-1 at 1; Compl. ¶ 4.) In a section of the Policy entitled Commercial Inland Marine Conditions, the Policy explains Assurance's right to subrogation. (Dkt. No. 42-1 at 14.) The section states "if any person or organization to or for whom we make payment under this Coverage Part has rights to recover damages from another, those rights are transferred to us to the extent of our payment." (Id. at 14.) These conditions "apply in addition to the Common Policy Conditions and applicable Additional Conditions in Commercial Inland Marine Coverage Forms." (Id.) The Policy contains a Builders Risk and Installation Coverage Form ("Coverage Form"), which covers certain losses and damages to property. (Id. at 12, 18.) This Coverage Form is part of the Policy and "is also subject to all Conditions in the . . . Commercial Inland Marine Conditions forms." (Id. at 18.) One such "Commercial Inland Marine Conditions forms" contains Assurance's right to subrogation set out above. (Id. at 14.)

Seavestco's work on the project was primarily focused on construction supervision and management. On or about February 11, 2005, Wellington contracted with Seavestco for such services. (Dkt. No. 32 at 7.) The Contract identified Randy Previs as the project manager with primary responsibility for supervision of Seavestco's work. (Id. at 8.) Previs is the principal of both Seavestco and Wellington. (Dkt. No. 40-1 at 4.) Under the Contract, Seavestco agreed to provide construction and sub-contractor management for Wellington sub-contracts, complete the entitlement process for buildings A and B, and construct the east and west walls, among other things. (Dkt. No. 32 at 7.) Under the Contract, termination was to occur "upon satisfactory completion of the work and final payment by the Owner." (Id. at 11.) The parties agreed the term "completion of work" meant "100% completion and not substantial completion." (Id. at 8.)

Assurance filed its complaint as Wellington's subrogee against both Seavestco and Premium. Assurance's complaint includes two separate causes of action against Seavestco: (1) breach of contract, and (2) negligence. Assurance claims Seavestco breached its agreement with Wellington, and its implied duty to perform its work in "a good and workerlike [sic] manner," when it blocked the retaining wall drain lines with six feet of compacted soil. (Compl. at ¶¶ 15-18.) Assurance's second cause of action is for negligence. Assurance alleges Seavestco breached its duty to perform its work in a reasonable manner when it blocked the retaining wall drain lines, failed to maintain open drain lines for the retaining wall, and failed to supervise the actions of its subcontractors or other contractors. (Id. at ¶¶ 19-22.)

Seavestco filed this summary judgment motion seeking dismissal of both claims. (Dkt. Nos. 31, 34.) First, Seavestco argues it is not liable for breach of contract because its contract with Wellington terminated before the retaining wall failed. (Dkt. No. 44 at 4.) Second, Seavestco contends the Court should dismiss Assurance's negligence cause of action because it is a claim for negligent construction, which is barred by Washington law. (Dkt. No. 31 at 6-7.) Third, Seavestco argues the Court should dismiss Assurance's claims because Wellington never assigned its rights to Assurance and that Assurance is not the subrogee. (Id. at 1-2.)

Analysis

A. Summary Judgment Standard

The Court "shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). The Court views the underlying facts in the light most favorable to the party opposing the motion. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986). The moving party has the burden to show the absence of a genuine issue of material fact. Adickes v. S.H. Kress & Co., 398 U.S. 144, 159 (1970). Once the moving party has met its initial burden, the nonmoving party must "designate specific facts showing that there is a genuine issue for trial." Celotex Corp. v. Catrett, 477 U.S. 317, 323-24 (1986). B. Breach of Contract

Summary judgment is not appropriate on Assurance's breach of contract claim because Seavestco cannot establish it completed its performance under the Contract prior to the accident.

Under the Contract between Seavestco and Wellington, termination occurs "upon satisfactory completion of the work and final payment by the Owner." (Dkt. No. 32 at 11.) The parties agreed the term "completion of work" meant "100% completion and not substantial completion." (Id. at 8.) Assurance does not dispute Seavestco received a final payment from Wellington. (Dkt. No. 39 at 7.) That does not end the inquiry, as there still must be evidence that Seavestco completed all work prior to loss. As explained below, it did not. (Id. at 7-8.)

Seavestco did not complete all of its work under the Contract prior to the loss, and cannot obtain dismissal of the breach of contract claim on the theory it was terminated prior to loss. Under the Contract, Seavestco agreed to provide construction management for Wellington subcontractors, complete the entitlement process for buildings A and B, and construct walls. (Dkt. No. 32 at 7.) None of these projects were complete prior to loss. First, Seavestco does not dispute that as of March 21, 2012, it has not yet completed the entitlement process for the Project. (Dkt. No. 40-1 at 9.) Second, Seavestco did not manage Wellington's subcontractors throughout construction, despite the fact the Contract required Previs to do so. (Dkt. No. 32 at 7-8.) Seavestco admits Previs did not manage the Project as the Seavestco Project Manager between February and December 2008. (Dkt. No. 44 at 2-3.) Third, Seavestco alleges that it did not work on the project between July 2008 and December 2008; rather, its employees became employees of Wellington during that time. (Dkt. No. 31 at 3.) Because Seavestco cannot show that it performed and completed the work, the Court cannot conclude the contract was terminated prior to loss. The Court DENIES the motion for summary judgment on Assurance's breach of contract claim. C. Negligence

Seavestco erroneously contends Assurance's negligence cause of action is a claim for negligent construction barred by Stuart v. Coldwell Banker, 109 Wn.2d 406, 421-22 (1987).

In Stuart, the Washington Supreme Court held that homeowners cannot bring tort actions for negligent construction based solely on economic loss because such loss must be remedied by contract law, not tort. Id. at 417-21. In Stuart, the plaintiff homeowner brought a cause of action against defendant developer for negligently constructing decks and walkways, which deteriorated from weather exposure. Id. at 410, 421.

Assurance does not pursue negligent construction claims. The complaint alleges Seavestco acted negligently when it blocked the retaining wall drain lines, failed to maintain open drain lines for the retaining wall, and failed to supervise the actions of its subcontractors or other contractors. (Id. at ¶¶ 19-22.) These are not claims for negligent construction, but rather for straight negligence. The rule in Stuart is not applicable. The Court DENIES Seavestco's motion on this issue. D. Subrogation

Seavestco incorrectly seeks dismissal of Assurance's claims on the theory that Assurance is not Wellington's proper subrogee.

There are two forms of subrogation, equitable and conventional. Mutual of Enumclaw Ins. Co. v. USF Ins. Co., 164 Wn.2d 411, 423 (2008). Under conventional subrogation, an insurer who receives full contractual assignment of an insured's rights may bring a conventional subrogation claim to enforce those rights. Id. at 424. The assignment of a right depends on the intent of the parties as shown in the contract. Old Nat'l Bank of Washington v. Arneson, 54 Wn. App. 717, 723 (1989).

Seavestco's has failed to show Assurance is not a valid subrogee, and the Court finds Assurance is entitled to conventional subrogation. The Policy here includes an express provision for subrogation, satisfying the conventional subrogation elements. Contrary to Seavestco's position, the Builder's Risk and Installation Coverage Form is not only part of the Policy, but it is subject to the subrogation arrangement. The Builder's Risk form is part of the Policy and it expressly incorporates the Commercial Inland Marine Conditions forms, one of which includes the subrogation agreement. (Dkt. No. 41-2 at 14, 18.) The Court DENIES Seavestco's motion on this issue. E. Motion to Strike

Defendant Premium filed a brief opposing Seavestco's motion for summary judgment and asks the Court to strike the declaration of Randy Previs for lack of personal knowledge and speculation over which contractor covered the drain pipe. (Dkt. No. 37.) Because the Court does not need to consider this information to reach a decision on this motion, it finds Premium's motion is MOOT.

Conclusion

The Court DENIES Seavestco's motion for summary judgment. Seavestco has failed to show it fully performed the contract prior to loss or that a legal defense to the breach of contract claim exists. Seavestco has also inaccurately construed Assurance's negligence claim as one for negligent construction. Because Assurance's claim is for negligence, not negligent construction, it is not barred and the Court denies Seavestco's request for its dismissal. Seavestco has also failed to demonstrate any deficiency in Assurance's status as a subrogee to Wellington.

The clerk is ordered to provide copies of this order to all counsel.

_________________

Marsha J. Pechman

United States District Judge


Summaries of

Assurance Co. of America v. Premium Constr. Grp., Inc.

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE
May 21, 2012
CASE NO. C11-1662 MJP (W.D. Wash. May. 21, 2012)
Case details for

Assurance Co. of America v. Premium Constr. Grp., Inc.

Case Details

Full title:ASSURANCE COMPANY OF AMERICA, Plaintiff, v. PREMIUM CONSTRUCTION GROUP…

Court:UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE

Date published: May 21, 2012

Citations

CASE NO. C11-1662 MJP (W.D. Wash. May. 21, 2012)